| SPI Eviction Invoicing Procedure Change |
| Tuesday, 07 December 2004 | |
|
A number of recent HUD audit results reported to us
by our clients have confirmed some specifics about HUD's
requirements for eviction invoicing. HUD requires that
debris removal and any other work performed on or around the date
of the eviction but not pursuant to the specific
instructions of the supervising sheriff be billed by the
cubic yard, not by man-hours. Moreover, HUD will
not accept invoices containing eviction work billed by
man-hours and debris removal billed by the cubic yard on
the same invoice. The new process will result in two invoices for each FHA eviction. The first invoice (the Eviction invoice) will reflect the date the eviction was completed and will include only the man-hour charges incurred for the eviction, i.e., work performed at the direction and under the control of the supervising sheriff. The second invoice (the Convey Maintenance invoice) will list the date of debris removal (which may be different from the eviction date) and will include any other costs incurred in connection with the eviction but completed for the purpose of putting the property in convey condition. As a result, each FHA eviction will now have two corresponding invoice numbers and two internal Safeguard order numbers. * Please also note that recent interpretations
support the position that personal property ordered by the sheriff
to be moved to the curb and left for 24 to 48 hours cannot then
be removed and billed by man-hours as part of the
eviction. Such items, if they are to be removed from the
curb and disposed of after the sheriff is no longer directly
supervising the work performed, must be removed by the cubic
yard. This removal is not considered part of the eviction
and is subject to the allowable cost limit for the jurisdiction;
therefore, if the removal will necessitate exceeding the allowable,
debris-bidding rules will apply. |